Sasha Durand
41%
30
Construction Permits
34 total
17
Currently Open
27
Rate-Eligible
permits > 1yr old
2015–2025
Years Active
Closure rate based on permits older than 1 year. “Issued” and “Stop Work” statuses are excluded.
Performance by Permit Type
Building27 rated
40.7% closed vs 30% median, 10.7 points higher
Median based on all applicants with 20+ rated permits in each category. Only permits older than 1 year are rated.
Year-by-Year Summary
2025
—
Open1
Closed2
Too early to rate — permits need 1 year to mature
2024
100.0%
Open0
Closed2
2 closed / 2 rated
2023
75.0%
Open1
Closed3
3 closed / 4 rated
2022
50.0%
Open1
Closed1
1 closed / 2 rated
2021
0.0%
Open1
Closed0
0 closed / 1 rated
2020
0.0%
Open1
Closed0
0 closed / 1 rated
2019
33.3%
Open2
Closed1
1 closed / 3 rated
2018
37.5%
Open5
Closed3
3 closed / 8 rated
2017
33.3%
Open2
Closed1
1 closed / 3 rated
2016
0.0%
Open2
Closed0
0 closed / 2 rated
2015
0.0%
Open1
Closed0
0 closed / 1 rated
All Permits
34 permits
| Status | Permit # | Address | Issued▼ | |||
|---|---|---|---|---|---|---|
| Open | SF1782362 | Short Form Bldg Permit | 2-10 Commonwealth AV, Boston | Oct 28, 2025<1yr | Apr 28, 2026 | $306,355.69 |
| Closed | SF1769860 | Short Form Bldg Permit | 1 Charles Street South, Boston | Sep 3, 2025<1yr | Mar 3, 2026 | $208,365 |
| Closed | SF1730733 | Short Form Bldg Permit | 134 Chestnut ST, Boston | Jun 27, 2025<1yr | Dec 27, 2025 | $355,475 |
| Closed | SF1638218 | Short Form Bldg Permit | 86 Beacon ST, Boston | Aug 15, 2024 | Feb 15, 2025 | $1,488,111 |
| Closed | SF1559592 | Short Form Bldg Permit | 141 Dorchester AV, South Boston | Jan 8, 2024 | Jul 8, 2024 | $65,767.2 |
| Closed | SF1545280 | Short Form Bldg Permit | 1 Huntington AV, Boston | Nov 30, 2023 | May 30, 2024 | $280,158 |
| Open | SF1493346 | Short Form Bldg Permit | 197 Commonwealth AV, Boston | Jul 14, 2023 | Jan 14, 2024 | $246,723.6 |
| Closed | ALT1472362 | Long Form/Alteration Permit | 20 Rowes WH, Boston | Jun 14, 2023 | Dec 14, 2023 | $15,000 |
| Closed | SF1472381 | Short Form Bldg Permit | 20 Rowes WH, Boston | May 12, 2023 | Nov 12, 2023 | $894,090 |
| Closed | SF1376722 | Short Form Bldg Permit | 143 W Concord ST, Roxbury | Sep 8, 2022 | Mar 8, 2023 | $301,429.2 |
| Open | SF1376918 | Short Form Bldg Permit | 71 Appleton ST, Boston | Aug 29, 2022 | Feb 28, 2023 | $499,675 |
| Closed | COO1174347 | Certificate of Occupancy | 2 Commonwealth AV, Boston | May 3, 2021 | — | $2,009,354 |
| Open | SF1146186 | Short Form Bldg Permit | 40-50 Battery ST, Boston | Jan 13, 2021 | Jul 13, 2021 | $126,000 |
| Closed | COO1125290 | Certificate of Occupancy | 1 Huntington AV, Boston | Dec 8, 2020 | — | $1,003,547.17 |
| Closed | COO1096197 | Certificate of Occupancy | 2-10 Commonwealth AV, Boston | Sep 14, 2020 | — | $637,000 |
| Open | SF1042520 | Short Form Bldg Permit | 505 Tremont ST, Boston | Jan 16, 2020 | Jul 16, 2020 | $863,363 |
| Closed | ALT973005 | Long Form/Alteration Permit | 1 Huntington AV, Boston | Jul 9, 2019 | Jan 9, 2020 | $12,825 |
| Open | SF973010 | Short Form Bldg Permit | 1 Huntington AV, Boston | Jul 8, 2019 | Jan 8, 2020 | $990,722.17 |
| Open | ALT892713 | Long Form/Alteration Permit | 2 Commonwealth AV, Boston | Jan 10, 2019 | Jul 10, 2019 | $1,989,354 |
| Open | SF892725 | Short Form Bldg Permit | 2 Commonwealth AV, Boston | Oct 23, 2018 | Apr 23, 2019 | $20,000 |
| Open | SF892888 | Short Form Bldg Permit | 12 Arlington ST, Boston | Oct 23, 2018 | Apr 23, 2019 | $324,403 |
| Open | ALT876238 | Long Form/Alteration Permit | 2-10 Commonwealth AV, Boston | Oct 11, 2018 | Apr 11, 2019 | $637,000 |
| Open | SF880359 | Short Form Bldg Permit | 2-10 Commonwealth AV, Boston | Sep 18, 2018 | Mar 18, 2019 | $0 |
| Closed | SF872897 | Short Form Bldg Permit | 36 Rutland SQ, Roxbury | Aug 27, 2018 | Feb 27, 2019 | $175,000 |
| Closed | SF871658 | Short Form Bldg Permit | 1293-1317 Washington ST, Roxbury | Aug 27, 2018 | Feb 27, 2019 | $200,000 |
| Open | SF827559 | Short Form Bldg Permit | 254 Commonwealth AV, Boston | May 7, 2018 | Nov 7, 2018 | $225,000 |
| Closed | SF790293 | Short Form Bldg Permit | 36 Rutland SQ, Roxbury | Jan 3, 2018 | Jul 3, 2018 | $85,000 |
| Closed | SF730799 | Short Form Bldg Permit | 2-10 Commonwealth AV, Boston | Jul 25, 2017 | Jan 25, 2018 | $325,000 |
| Open | SF675538 | Short Form Bldg Permit | 280 Commonwealth AV, Boston | Jan 31, 2017 | Jul 31, 2017 | $54,000 |
| Open | SF675524 | Short Form Bldg Permit | 1 Charles ST, Boston | Jan 31, 2017 | Jul 31, 2017 | $225,000 |
| Open | SF562955 | Short Form Bldg Permit | 220-200 Boylston ST, Boston | Feb 18, 2016 | Aug 18, 2016 | $130,000 |
| Open | SF562610 | Short Form Bldg Permit | 220-200 Boylston ST, Boston | Feb 12, 2016 | Aug 12, 2016 | $85,000 |
| Open | SF543087 | Short Form Bldg Permit | 20-22 Liberty DR, Boston | Nov 30, 2015 | May 30, 2016 | $370,000 |
| Closed | COO447425 | Certificate of Occupancy | 2 Commonwealth AV, Boston | Feb 24, 2015 | — | $1,239,500 |